Project Update: St. Mary’s Gymnasium & Fine Arts Building

Work on St. Mary’s Gymnasium and Fine Arts Center is moving forward.  This week the subcontractors continued to install the rough wiring, mechanical systems, and insulation.  The drywall crew has started to sheetrock the classrooms.  Things are bit dark inside with a roof on, and no light fixtures just yet, but that’s just a normal stage of the project.   It will make for a dramatic difference in another couple of weeks.

Three story masonry building is up and has the metal roof installed.

100dpi-01631

Classrooms are getting sheetrock on the walls.

100dpi-01625

There are great views across the Rogue Valley from the new aerobics room on the West Side of the Building.

100dpi-01628

The mechanical room is starting fill up with chillers, blowers, and ducts.

100dpi-01626

The gymnasium.

100dpi-01630