Public Category

N. Medford Highschool Media Center

Thursday, April 22nd, 2010

North Medford High School- 1900 North Keeneway Drive, Medford, OR 97504

Size:
9,000 SF Addition
9,500 SF Renovation

Construction Services: Competitive Bid General Contracting
Facility Category
:   School/Library
Architects
:  Mahlum and Associates
DWA Architects
Project Manager: Scott Heroux
Superintendent:  Sean Worthington

This addition and renovation project was done in three phases to accommodate the school year and temporary relocations during the project.

In Phase 1 during the summer of 2009, renovation work was done on existing student restrooms, and also on storage areas for the library, this was in preparation for the future expansion into the addition.  This phase was completed before students returned in the fall.

Phase 2  was also started in summer of 2009.  The addition of 9000 SF for a new library and three new classrooms continued into the fall.  The walls and entrances to the new areas, were kept closed during this time.   This allowed construction on the addition to proceed even while school was in session.  This phase did have an exacting completion deadline for the students winter break.  During winter break, the school staff was scheduled quickly vacate the old library, to allow abatement crews to remove asbestos in the old library while the school was empty for the holidays.

Phase 3 began after Christmas break and completely renovated the former 9000 SF library space for a new student commons area.

Siskiyou Hall- Southern Oregon University

Thursday, April 22nd, 2010

Siskiyou Hall- Southern Oregon University
Ashland, OR

Completed: 2004
Size: 12,200
Services: Competitive Bid
Facility Category: School/Housing
Architect: Ray Kistler
Project Manager: Andy McHugh
Superintendent: Roger Fisher

Construction was done by Batzer Construction and the 4 story brick and stucco building features a beautiful steel and storefront glazing lounge areas on all floors.   It includes Three-story dormitory, a computer center, and learning labs .  Construction work was completed during the school year on the busy campus.

IVFD- Administrative Headquarters

Wednesday, December 9th, 2009

Illinois Valley Fire District
Administrative Headquarters-  681 Caves Hwy, Cave Junction, OR

IVFD HQ

Completed:  2006
Size:  4,838 SF
Services: Design/Build
Facility Category:  Essential Services/911
Architect:  Mark McKechnie
Project Manager: Scott Heroux
Superintendent: Vane Jones

O’Brien Fire Station

Wednesday, December 9th, 2009

Illinois Valley Fire District
O’Brien Fire Station- 10 Lone Mountain Rd, O’Brien, OR

Completed:  2005
Size:  5,892 SF
Services: Design/Build
Facility Category:  Essential Services/911
Architect:  Mark McKechnie
Project Manager: Scott Heroux
Superintendent: Vane Jones

Cave Junction Fire Station

Wednesday, December 9th, 2009

Illinois Valley Fire District
Cave Junction Fire Station-  681 Caves Hwy, Cave Junction, OR

Completed:  2005
Size:  6,300 SF
Services: Design/Build
Facility Category:  Essential Services/911
Architect:  Mark McKechnie
Project Manager: Scott Heroux
Superintendent: Vane Jones

6,300 SF fire station, included living quarters

Roosevelt Elementary School

Wednesday, December 9th, 2009

Medford School District #549C
Roosevelt Elementary School-  112 Lindley St., Medford, OR 97504

Completed: 2009
Size: 48,200 SF
Services: Competitive Bid General Contracting
Facility Category:  School
Architect
: Opsis Architecture and
The Abell Architectural Group
Project Manager: Brett Smith

The team designed renovations and restoration of the school’s historic 1949 addition and also added a new two-story elementary school and detached gymnasium.   Educational areas included learning studios (classrooms) with associated project commons areas, outdoor learning areas, building commons, library/media center, music/multi purpose, computer lab, restrooms, and administrative offices.

Jackson Elementary School

Wednesday, December 9th, 2009

Medford School District 549C
Jackson Elementary School- 630 W. Jackson Street, Medford, OR 97501

Interior

Completed:  2009
Size
:  52,600 SF
Services
: Competitive Bid General Contracting
Facility Category
:  School
Architect
: Opsis Architecture and
The Abell Architectural Group
Project Manager
: Brett Smith
Superintendent
: John Nelson

This sister project to Roosevelt elementary was originally built 1911 and had the same 1949 addition.   In 2008 we renovated and restored the historic 1949 section of the existing school and built a new two-story elementary school and detached gymnasium, including learning studios (classrooms) with associated project commons areas, outdoor learning areas, building commons, library/media center, music/multi purpose, computer lab, restrooms, and administrative offices.

White City Elementary School

Wednesday, December 9th, 2009

White City Elementary School- 2830 Maple Court, White City, OR 97503

Completed: 2004
Size: 42,000 SF
Services
:Competitive Bid General Contracting
Facility Category
:  School

This new school constructed in 2004 serves as a case study for sustainability and energy efficiency in Oregon.

Some of the measures incorporated into the design included the following:

  • The school uses daylighting extensively. Daylighting is the controlled admission of natural light into a space through windows, skylights, or roof monitors.
  • Sunshades are installed on the outside of the South side of the building to prevent excessive heat gain.
  • The school equipped classrooms with fluorescent lighting fixtures with T-5 lamps and energy efficient ballasts. All lights have occupancy sensors that are estimated to reduce lighting usage by 30 percent.
  • Classroom windows are operable allowing for natural ventilation.
  • Two central, natural gas-fired boilers heat the hot water for the school. They have thermal efficiencies of 88 percent compared to the code standard efficiency of 80 percent.
  • Nearly all of the waste generated during construction was recycled.
  • The school has low or no-VOC (Volatile Organic Compounds) paints, varnishes, adhesives etc. that can be harmful to health.
  • The plantings are drought resistant species.
  • There is a drip irrigation system that can be used sparingly once plants are established.
  • Water is stored and pre-cooled in three underground tanks before it goes to the chiller so the chiller
    doesn’t have to operate as long or as frequently.
  • A bioswale and pond system in the hillside behind the school holds and filters rain run-off before it
    enters the city storm system. The area is planted with native vegetation and does not require irrigation
    or maintenance. The ponds resemble dry lake beds that fill with rain water that is then gradually
    released to the storm system.
  • A bicycle parking area is big enough for 95 percent of children if they ride bikes to school.
  • The school “envelope” (floor, walls and ceiling) has excellent insulation. Part of the building is actually built into the hillside.
  • Low-flow plumbing fixtures; timed water faucets that turn off automatically.
  • Multi-purpose areas. The music room can be used as a community room; the gym and cafeteria have
    a stage in between that can be accessed from either side; three special education rooms can be opened
    to make one big room when required. The gym, cafeteria, and community room have a separate entrance so they can be opened for evening and weekend events without accessing other parts of the building, which saves on heating & lighting needs.
  • From the Eagle Rock Case Study (a matching sister school)

Eagle Rock Elementary School

Wednesday, December 9th, 2009

Eagle Rock Elementary School- 1280 Barton Road, Eagle Point, OR 97524-4407

eaglerock

Completed: 2004
Size: 42,000 SF
Services: Competitive Bid General Contracting
Facility Category:  School

This new school constructed in 2004 serves as a case study for sustainability and energy efficiency in Oregon.

  • The school uses daylighting extensively. Daylighting is the controlled admission of natural light into a space through windows, skylights, or roof monitors.
  • Sunshades are installed on the outside of the South side of the building to prevent excessive heat gain.
  • The school equipped classrooms with fluorescent lighting fixtures with T-5 lamps and energy efficient ballasts. All lights have occupancy sensors that are estimated to reduce lighting usage by 30 percent.
  • Classroom windows are operable allowing for natural ventilation.
  • Two central, natural gas-fired boilers heat the hot water for the school. They have thermal efficiencies of 88 percent compared to the code standard efficiency of 80 percent.
  • Nearly all of the waste generated during construction was recycled.
  • The school has low or no-VOC (Volatile Organic Compounds) paints, varnishes, adhesives etc. that can be harmful to health.
  • The plantings are drought resistant species.
  • There is a drip irrigation system that can be used sparingly once plants are established.
  • Water is stored and pre-cooled in three underground tanks before it goes to the chiller so the chiller
    doesn’t have to operate as long or as frequently.
  • A bioswale and pond system in the hillside behind the school holds and filters rain run-off before it
    enters the city storm system. The area is planted with native vegetation and does not require irrigation
    or maintenance. The ponds resemble dry lake beds that fill with rain water that is then gradually
    released to the storm system.
  • A bicycle parking area is big enough for 95 percent of children if they ride bikes to school.
  • The school “envelope” (floor, walls and ceiling) has excellent insulation. Part of the building is actually built into the hillside.
  • Low-flow plumbing fixtures; timed water faucets that turn off automatically.
  • Multi-purpose areas. The music room can be used as a community room; the gym and cafeteria have
    a stage in between that can be accessed from either side; three special education rooms can be opened
    to make one big room when required. The gym, cafeteria, and community room have a separate entrance so they can be opened for evening and weekend events without accessing other parts of the building, which saves on heating & lighting needs.

    From the Oregon Department of Energy Eagle_Rock Case Study

DMV & Red Cross

Wednesday, December 9th, 2009

DMV/Red Cross- 1174 Progress Drive, #103, Medford, OR

DMV

Completed: 2000
Size: 15,000 SF
Services: Design/Build
Facility Category:  Office
Architect: Chuck Beck, AIA
Project Manager: Bud Lee
Superintendent: Roger Fisher

This massive renovation of the old Medford 4 Cinemas, included a complete re-construction of the building on the exterior and interior.   The building was structurally improved for seismic (earthquake) issues.  The interior includes an attractive office lobby, and plenty of office space.    Currently the Oregon Department of Motor Vehicles and the Red Cross share the space.  The building is owned and operated by Biddle Rd. Leasing, LLC.

Creswell Bus Barn

Wednesday, December 9th, 2009

Creswell Bus Barn- 998 W. A Street, Creswell, OR

CreswellBusBarn (1 of 1)

Completed:  2008
Size:            6500 SF
Services: Design/Build
Facility Category:  Shop/Garage
Architect: Mary Pearch, gLAs
Project Manager: Andy McHugh
Superintendent: Russ Dodd

Martha Young Family Service Center

Tuesday, December 8th, 2009

United Community Action Network  (UCAN)
Martha Young Family Service Center-280 Kenneth Ford Dr., Roseburg, OR

Completed: 2008
Size
: 11,548 SF
Services
: Competitive Bid General Contracting
Architect
: Pinnacle Architecture Inc.
Project Manager: Carl Tullis
Superintendent: Sven Flatebo

This office houses several different family service agencies:  Energy Assistance and Education, Rental/Mortgage Assistance and Counseling, Homeless Assistance, Child Care Provider Support and Resources, Administrative Services.  The building provides the agencies with conference space, private meeting areas for working with families, a reception area, break room, copy room, and office supply storage.

UCAN-1023

Vehicle Storage Facility

Monday, December 7th, 2009

Ashland  Electric – 90 N. Mountain Avenue, Ashland, OR 97520

AshlandElectric

Completed:  2008
Size:           9,240 SF
Services: Competitive Bid Design/Build
Facility Category:  Shop/Garage
Architect: Architectural Design Works
Project Manager: Carl Tullis
Superintendent: John Nelson

This vehicle storage barn remodel was completed in phases to suit the client’s budget.   The metal exterior and roof of an existing building were replaced and pre-set for future installation of solar panels.  From the start everyone knew that eventually a large installation of solar panels would be installed.  One year after the remodeling preparations, the City of Ashland had the funding in place to complete the project and they were easily able to install 62 kW of power production on their truck storage building.

Selma Fire Station

Monday, December 7th, 2009

Illinois Valley Fire District
Selma Fire Station- 28195 Redwood HWY, Selma, OR 97523

Completed:  2005
Size:  7836 SF
Services: Design/Build
Facility Category:  Essential Services/911
Architect:  Mark McKechnie
Project Manager: Scott Heroux
Superintendent: Vane Jones

The Selma Fire station was one of 3 fire stations done for IVFD in 2005 .  The stations are designed for easy storage of equipment and efficient response time to fires.

“Our profound thanks for a most positive professional experience that benfitted this fire district and our numerous surrounding communities.”  — Harry Rich, Fire Chief

Creswell Middle School

Monday, December 7th, 2009

Creswell Middle School-  655 West Oregon Ave., Creswell, OR

Gym

Completed:  2009
Size
:  77,400 SF
Services
: Competitive Bid General Contracting
Facility Category
:  School
Architect
:gLAs
Project Manager
: Andy McHugh
Superintendent
: Russ Dodd

This was a new construction project of a  two story school building including new  library, gym, kitchen, and cafeteria. The new  school was built while students were in school on the adjacent property.  Extensive safety measures were taken to assure students were protected and safe at all times. Upon completion, the old school was demolished and the site was restored for new parking areas.

The playing fields have been completely resurfaced with high performance artificial turf specifically designed to withstand the sports and play activity during the rainy season of  an Oregon school year.